Skip to main content

Heritage Heights, Matunga

Ready to moveLapsed

by Gold Star Builders & Developers PvtLtd · Matunga, Mumbai 400019 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
20.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
5
3 BHK
17
Total units
22
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%–
100%100%95%–
100%100%95%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400019

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths3 yrs 10 mths
Possession date extendedBy 1 yr3 of 3
Possession date (MahaRERA)Dec 2020Sep 2026
Concrete structure (RCC)100%92%
Units booked–91%
MahaRERA complaints (filed by or against the builder)11

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Heritage Heights by Gold Star Builders & Developers PvtLtd is a 22-unit project in Matunga, Mumbai 400019, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Heritage Heights is a project by Gold Star Builders & Developers PvtLtd in Matunga, Mumbai 400019, registered with MahaRERA as P51900006038. It was launched in August 2017. It has 22 units in 2 buildings, with 1 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.