Siddharth Enclave, Lower Parel

Ready to move

by Siddharth Developers · Lower Parel, Mumbai 400013 · Map

Launched
Jul 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Jun 2025Extended by 5 yrs 6 mths
Concrete structure
100%Ready to move
Booked
64 of 6894%
Buildings
20.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
62
2 BHK
6
Total units
68
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services93%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 93%Dec 2025: Final finishes 93%Jul 2026: Final finishes 93%Excavation 100%Concrete structure (RCC) 100%Final finishes 93%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%93%64
100%100%93%64
100%100%93%62

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400013

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400013
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths4 yrs 4 mths
Possession date extendedBy 5 yrs 6 mths4 of 5
Possession date (MahaRERA)Jun 2025Dec 2023
Concrete structure (RCC)100%60%
Units booked94%60%
MahaRERA complaints (filed by or against the builder)10

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Siddharth Enclave by Siddharth Developers is a 68-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, launched in July 2017 with possession due in June 2025. 64 units booked out of total 68 units. The concrete structure (RCC) is complete.

Read full summary

Siddharth Enclave is a BMC-sanctioned project by Siddharth Developers in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900001979. It was launched in July 2017. It has 68 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in June 2025, after an extension of 5 years 6 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 93% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

64 units booked out of total 68 units (94%).