- Launched
- Jul 20177 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 116 of 116100% · 461 rehab units
- Buildings
- 51.4 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale116 booked out of 116 units
Rehab461 units for existing members
Total 577 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 129
- 2 BHK
- 69
- 3 BHK
- 69
- 4 BHK
- 4
- 5+ BHK
- 3
- Other units
- 303
- Total units
- 577
- Buildings
- 5
- Land
- 1.4 acres
- Phases
- 1
- MahaRERA complaints
- 4
- Free-sale units
- 116
- Rehab units
- 461
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 92% | 116 | |
| 100% | 100% | 92% | 116 | |
| 100% | 100% | 92% | 103 |
"–" means MahaRERA shows no figure for that update.
About this project
Shreepati Castle by Shreepati Castle is a 577-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in July 2017; its MahaRERA registration has lapsed. 116 units booked out of 116 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shreepati Castle is a BMC-sanctioned project by Shreepati Castle in Girgaon, Mumbai 400004, registered with MahaRERA as P51900002235. It was launched in July 2017. It has 577 units in 5 buildings: 274 homes (1, 2, 3, 4 and 5+ BHK) and 303 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 577 units, 116 are for sale and 461 are rehab units for existing members.
Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 92% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
116 units booked out of 116 units for sale (100%).
Shreepati's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 2,745 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 5 |
| Possession date extended on the builder's application | 3 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Shreepati projects | 8 (3 of 9 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.