Lifescapes Shubham, Girgaon

Lapsed

by Rohan Developers Pvt Ltd · Girgaon, Mumbai 400004 · Map

Launched
Aug 20175 yrs 10 mths originally promised
Possession (MahaRERA)
May 2025Extended by 1 yr 11 mthsWhat does Lapsed mean?
Concrete structure
98%Mid-construction
Booked
138 of 15490%
Buildings
31.3 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
100
3 BHK
54
Total units
154
Buildings
3
Land
1.3 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)98%
Finishes, lifts and services33%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 98%Dec 2025: Concrete structure (RCC) 98%Jul 2026: Concrete structure (RCC) 98%Oct 2026: Concrete structure (RCC) 98%Dec 2024: Final finishes 33%Dec 2025: Final finishes 33%Jul 2026: Final finishes 33%Oct 2026: Final finishes 33%Excavation 100%Concrete structure (RCC) 98%Final finishes 33%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%33%138
100%98%33%–
100%98%33%–
100%98%33%138

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400004

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400004
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 10 mths5 yrs 8 mths
Possession date extendedBy 1 yr 11 mths3 of 4
Possession date (MahaRERA)May 2025Nov 2026
Concrete structure (RCC)98%100%
Units booked90%70%
MahaRERA complaints (filed by or against the builder)20

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Lifescapes Shubham by Rohan Developers Pvt Ltd is a 154-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in August 2017; its MahaRERA registration has lapsed. 138 units booked out of total 154 units. The concrete structure (RCC) is 98% complete.

Read full summary

Lifescapes Shubham is a BMC-sanctioned project by Rohan Developers Pvt Ltd in Girgaon, Mumbai 400004, registered with MahaRERA as P51900002696. It was launched in August 2017. It has 154 units in 3 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in May 2025, after an extension of 1 year 11 months from the original June 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 98% complete, final finishes 33% complete.

138 units booked out of total 154 units (90%).