Krishvi Heights, Girgaon

Ready to move

by M/s Shagun Associates · Girgaon, Mumbai 400004 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2022Extended by 3 yrs
Concrete structure
100%Ready to move
Booked (free sale)
27 of 3187% · 99 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale27 booked out of 31 units

Rehab99 units for existing members

Total 130 units. Rehab units are not for sale.

Project facts

1 BHK
63
2 BHK
24
3 BHK
19
4 BHK
3
Other units
21
Total units
130
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
31
Rehab units
99

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 82%Dec 2025: Concrete structure (RCC) 82%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 20%Dec 2025: Final finishes 20%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%27
100%82%20%–
100%82%20%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400004

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400004
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths6 yrs 1 mth
Possession date extendedBy 3 yrs5 of 6
Possession date (MahaRERA)Dec 2022Nov 2026
Concrete structure (RCC)100%100%
Units booked (free sale)87%86%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Krishvi Heights by M/s Shagun Associates is a 130-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in August 2017 with possession due in December 2022. 27 units booked out of 31 units for sale. The concrete structure (RCC) is complete.

Read full summary

Krishvi Heights is a BMC-sanctioned project by M/s Shagun Associates in Girgaon, Mumbai 400004, registered with MahaRERA as P51900004674. It was launched in August 2017. It has 130 units in 1 building: 109 homes (1, 2, 3 and 4 BHK) and 21 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 130 units, 31 are for sale and 99 are rehab units for existing members.

Possession was due in December 2022, after an extension of 3 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

27 units booked out of 31 units for sale (87%).