Ruparel Ariana, Sewri
Lapsed
by Shree Siddhivinayak Classic Construction pvt Ltd · Sewri, Mumbai 400015 · Map
- Launched
- Aug 20175 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 45%Mid-construction
- Booked
- –
- Buildings
- 23.1 acres
- MahaRERA complaints
- 30Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Total units
- –
- Buildings
- 2
- Land
- 3.1 acres
- Phases
- 1
- MahaRERA complaints
- 30
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 45% | 15% | – | |
| 50% | 45% | 15% | – | |
| 50% | 45% | 15% | 155 |
"–" means MahaRERA shows no figure for that update.
About this project
Ruparel Ariana by Shree Siddhivinayak Classic Construction pvt Ltd (Ruparel) is an SRA-sanctioned project in Sewri, Mumbai 400015, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 45% complete.
Read full summary
Ruparel Ariana is an SRA-sanctioned project by Shree Siddhivinayak Classic Construction pvt Ltd in Sewri, Mumbai 400015, registered with MahaRERA as P51900003250. It was launched in August 2017. Its MahaRERA status is Lapsed.
Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation 50% complete, structure (RCC) 45% complete, final finishes 15% complete.
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.