Om Shree Janabai, Dadar West

by Signet Properties Private Limited · Dadar West, Mumbai 400028 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 1 yr
Concrete structure
93%Mid-construction
Booked (free sale)
16 of 6027% · 52 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 60 units

Rehab52 units for existing members

Total 112 units. Rehab units are not for sale.

Project facts

1 BHK
37
Other units
75
Total units
112
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
60
Rehab units
52

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)93%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 93%Jul 2026: Concrete structure (RCC) 93%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 93%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%93%0%16
100%93%0%16
100%90%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths4 yrs
Possession date extendedBy 1 yr6 of 6
Possession date (MahaRERA)Dec 2023Jun 2024
Concrete structure (RCC)93%95%
Units booked (free sale)27%75%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Om Shree Janabai by Signet Properties Private Limited is a 112-unit SRA-sanctioned project in Dadar West, Mumbai 400028, launched in August 2017 with possession due in December 2023. 16 units booked out of 60 units for sale. The concrete structure (RCC) is 93% complete.

Read full summary

Om Shree Janabai is an SRA-sanctioned project by Signet Properties Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as P51900004251. It was launched in August 2017. It has 112 units in 1 building: 37 homes (1 BHK) and 75 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 112 units, 60 are for sale and 52 are rehab units for existing members.

Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 93% complete, final finishes not started.

16 units booked out of 60 units for sale (27%).