Ready to moveLapsed

by M/S. Om Siddhi Venture · Dadar West, Mumbai 400028 · Map

Launched
Aug 20173 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 5 yrsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
48 of 5489%
Buildings
20.5 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
9
3 BHK
2
4 BHK
19
5+ BHK
19
Other units
5
Total units
54
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services93%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 98%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 93%Jul 2026: Final finishes 93%Oct 2026: Final finishes 93%Excavation 100%Concrete structure (RCC) 100%Final finishes 93%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%93%48
100%100%93%48
100%100%93%48
100%98%50%47

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths4 yrs 8 mths
Possession date extendedBy 5 yrs6 of 6
Possession date (MahaRERA)Dec 2025Mar 2024
Concrete structure (RCC)100%96%
Units booked89%62%
MahaRERA complaints (filed by or against the builder)20

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Om Siddhi Sra Chs Ltd by M/S. Om Siddhi Venture is a 54-unit SRA-sanctioned project in Dadar West, Mumbai 400028, launched in August 2017; its MahaRERA registration has lapsed. 48 units booked out of total 54 units. The concrete structure (RCC) is complete.

Read full summary

Om Siddhi Sra Chs Ltd is an SRA-sanctioned project by M/S. Om Siddhi Venture in Dadar West, Mumbai 400028, registered with MahaRERA as P51900010775. It was launched in August 2017. It has 54 units in 2 buildings: 49 homes (1, 3, 4 and 5+ BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 5 years from the original December 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 93% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

48 units booked out of total 54 units (89%).