Sodah Sadan, Matunga

Ready to moveLapsed

by Unispace Landmark Private Limited · Matunga, Mumbai 400019 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Jun 2023Extended by 4 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
6 of 786%
Buildings
10.1 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
2
2 BHK
1
3 BHK
1
Other units
3
Total units
7
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%6
100%100%95%–
100%100%95%–
100%100%95%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400019

Projects with up to 10 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 4 mths1 yr 4 mths
Possession date extendedBy 4 yrs 6 mths2 of 3
Possession date (MahaRERA)Jun 2023Dec 2022
Concrete structure (RCC)100%0%
MahaRERA complaints (filed by or against the builder)32

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sodah Sadan by Unispace Landmark Private Limited is a 7-unit project in Matunga, Mumbai 400019, launched in August 2017; its MahaRERA registration has lapsed. 6 units booked out of total 7 units. The concrete structure (RCC) is complete.

Read full summary

Sodah Sadan is a project by Unispace Landmark Private Limited in Matunga, Mumbai 400019, registered with MahaRERA as P51900006024. It was launched in August 2017. It has 7 units in 1 building: 4 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2023, after an extension of 4 years 6 months from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

6 units booked out of total 7 units (86%).