Tridhaatu Aaroha, Matunga
Lapsed
by Tridhaatu Vishnu Kunj Developers LLP · Matunga, Mumbai 400019 · Map
- Launched
- Aug 20171 yr 1 mth originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 5 yrs 3 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 8 of 8100%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 1
- 3 BHK
- 6
- 4 BHK
- 1
- Total units
- 8
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 85% | 8 | |
| 100% | 100% | 85% | – | |
| 100% | 100% | 85% | – | |
| 100% | 100% | 85% | 8 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400019
Projects with up to 20 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 1 mth | 1 yr 4 mths |
| Possession date extended | By 5 yrs 3 mths | 3 of 4 |
| Possession date (MahaRERA) | Dec 2023 | Mar 2023 |
| Concrete structure (RCC) | 100% | 50% |
| Units booked | 100% | 86% |
| MahaRERA complaints (filed by or against the builder) | 1 | 2 |
The 4 projects
- Shree Krishna Niwas, Matunga
- Versatile Heights, Matunga
- Sangeet Jyoti, Matunga
- Sodah Sadan, Matunga
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Krishna Niwas | August 2017 | December 2022 | 0% | – |
| Versatile Heights | August 2017 | October 2020 | 0% | 9 units booked out of total 10 units |
| Sangeet Jyoti | August 2017 | June 2025 | 100% | 5 units booked out of total 11 units |
| Sodah Sadan | August 2017 | June 2023 | 100% | 6 units booked out of total 7 units |
About this project
Tridhaatu Aaroha by Tridhaatu Vishnu Kunj Developers LLP is an 8-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in August 2017; its MahaRERA registration has lapsed. 8 units booked out of total 8 units. The concrete structure (RCC) is complete.
Read full summary
Tridhaatu Aaroha is a BMC-sanctioned project by Tridhaatu Vishnu Kunj Developers LLP in Matunga, Mumbai 400019, registered with MahaRERA as P51900010312. It was launched in August 2017. It has 8 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023, after an extension of 5 years 3 months from the original September 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.
8 units booked out of total 8 units (100%).
Tridhaatu's track record in Mumbai
MahaRERA projects registered 2017–2023 in Mumbai
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 649 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 1 |
| Lapsed | 6 |
| Under construction | 4 |
| Possession date extended on the builder's application | 6 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Tridhaatu projects | 33 (10 of 12 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.