Skip to main content

Tridhaatu Aaroha, Matunga

Lapsed

by Tridhaatu Vishnu Kunj Developers LLP · Matunga, Mumbai 400019 · Map

Launched
Aug 20171 yr 1 mth originally promised
Possession (MahaRERA)
Dec 2023Extended by 5 yrs 3 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
8 of 8100%
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
1
3 BHK
6
4 BHK
1
Total units
8
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services85%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 85%Dec 2025: Final finishes 85%Jul 2026: Final finishes 85%Oct 2026: Final finishes 85%Excavation 100%Concrete structure (RCC) 100%Final finishes 85%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%85%8
100%100%85%–
100%100%85%–
100%100%85%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400019

Projects with up to 20 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 1 mth1 yr 4 mths
Possession date extendedBy 5 yrs 3 mths3 of 4
Possession date (MahaRERA)Dec 2023Mar 2023
Concrete structure (RCC)100%50%
Units booked100%86%
MahaRERA complaints (filed by or against the builder)12

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Tridhaatu Aaroha by Tridhaatu Vishnu Kunj Developers LLP is an 8-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in August 2017; its MahaRERA registration has lapsed. 8 units booked out of total 8 units. The concrete structure (RCC) is complete.

Read full summary

Tridhaatu Aaroha is a BMC-sanctioned project by Tridhaatu Vishnu Kunj Developers LLP in Matunga, Mumbai 400019, registered with MahaRERA as P51900010312. It was launched in August 2017. It has 8 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023, after an extension of 5 years 3 months from the original September 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.

8 units booked out of total 8 units (100%).

Tridhaatu's track record in Mumbai

MahaRERA projects registered 2017–2023 in Mumbai

Projects registered with MahaRERA12
Total units across these projects649
Completed without extending the possession date1
Completed after an extension1
Lapsed6
Under construction4
Possession date extended on the builder's application6
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Tridhaatu projects33 (10 of 12 projects)

See all Tridhaatu projects →