Continental Heights, Mazgaon

by Sarah Housing Development Pvt Ltd · Mazgaon, Mumbai 400010 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2029Extended by 5 yrs
Concrete structure
94%Mid-construction
Booked
–
Buildings
11.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
132
2 BHK
128
3 BHK
54
Other units
13
Total units
328
Buildings
1
Land
1.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)94%
Finishes, lifts and services78%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 94%Dec 2025: Concrete structure (RCC) 94%Jul 2026: Concrete structure (RCC) 94%Dec 2024: Final finishes 78%Dec 2025: Final finishes 78%Jul 2026: Final finishes 78%Excavation 100%Concrete structure (RCC) 94%Final finishes 78%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%94%78%–
100%94%78%–
100%94%78%268

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400010

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400010
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 4 mths4 yrs 7 mths
Possession date extendedBy 5 yrs3 of 4
Possession date (MahaRERA)Dec 2029Aug 2026
Concrete structure (RCC)94%64%
Units booked–82%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Continental Heights by Sarah Housing Development Pvt Ltd is a 328-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in August 2017 with possession due in December 2029. The concrete structure (RCC) is 94% complete.

Read full summary

Continental Heights is a BMC-sanctioned project by Sarah Housing Development Pvt Ltd in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900007187. It was launched in August 2017. It has 328 units in 1 building: 315 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 5 years from the original December 2024. Construction: excavation complete, structure (RCC) 94% complete, final finishes 78% complete.