Tarabaug, Mazgaon

by Darshan Developers · Mazgaon, Mumbai 400010 · Map

Launched
Aug 20179 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2032Extended by 6 yrs
Concrete structure
61%Mid-construction
Booked (free sale)
103 of 12185% · 332 rehab units
Buildings
82.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale103 booked out of 121 units

Rehab332 units for existing members

Total 453 units. Rehab units are not for sale.

Project facts

1 RK
2
1 BHK
248
2 BHK
163
3 BHK
28
Other units
12
Total units
453
Buildings
8
Land
2.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
121
Rehab units
332

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation63%
Concrete structure (slabs)61%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 64%Dec 2025: Excavation 64%Jul 2026: Excavation 50%Oct 2026: Excavation 63%Dec 2024: Concrete structure (RCC) 9%Dec 2025: Concrete structure (RCC) 9%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 61%Dec 2024: Final finishes 41%Dec 2025: Final finishes 41%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 63%Concrete structure (RCC) 61%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
63%61%50%103
50%50%50%103
64%9%41%–
64%9%41%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400010

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400010
MeasureThis projectSimilar projects
Launch to possession (as first promised)9 yrs 4 mths4 yrs 7 mths
Possession date extendedBy 6 yrs3 of 4
Possession date (MahaRERA)Dec 2032Aug 2026
Concrete structure (RCC)61%74%
Units booked (free sale)85%79%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Tarabaug by Darshan Developers is a 453-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in August 2017 with possession due in December 2032. 103 units booked out of 121 units for sale. The concrete structure (RCC) is 61% complete.

Read full summary

Tarabaug is a BMC-sanctioned project by Darshan Developers in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900008495. It was launched in August 2017. It has 453 units in 8 buildings: 441 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 453 units, 121 are for sale and 332 are rehab units for existing members.

Its registered possession date is December 2032, extended by 6 years from the original December 2026. Construction: excavation 63% complete, structure (RCC) 61% complete, final finishes 50% complete.

103 units booked out of 121 units for sale (85%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 50% to 61%.