Anzar Residency, Mumbai Central
by Mithila Developers · Mumbai Central, Mumbai 400008 · Map
- Launched
- Sep 20174 yrs 3 mths originally promised
- Possession (MahaRERA)
- Apr 2029Extended by 7 yrs 4 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 0 of 310% · 33 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 31 units
Rehab33 units for existing members
Total 64 units. Rehab units are not for sale.
Project facts
- 1 RK
- 11
- 1 BHK
- 19
- 2 BHK
- 13
- 3 BHK
- 19
- Other units
- 2
- Total units
- 64
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 31
- Rehab units
- 33
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 0 | |
| 100% | 100% | 50% | 0 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400008
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 3 yrs 9 mths |
| Possession date extended | By 7 yrs 4 mths | 3 of 4 |
| Possession date (MahaRERA) | Apr 2029 | Aug 2026 |
| Concrete structure (RCC) | 100% | 90% |
| MahaRERA complaints (filed by or against the builder) | 1 | 4 |
The 4 projects
- Nemat -E- Farooque Heritage, Mumbai Central
- Ekdant, Mumbai Central
- Ndw The Crest, Mumbai Central
- Gulmohar Terrace, Mumbai Central
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nemat -E- Farooque Heritage | September 2017 | April 2027 | 70% | – |
| Ekdant | August 2017 | July 2024 | 100% | – |
| Ndw The Crest | August 2017 | December 2025 | 90% | – |
| Gulmohar Terrace | October 2017 | April 2028 | 90% | 46 units booked out of total 102 units |
About this project
Anzar Residency by Mithila Developers is a 64-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in September 2017 with possession due in April 2029. 0 units booked out of 31 units for sale. The concrete structure (RCC) is complete.
Read full summary
Anzar Residency is a BMC-sanctioned project by Mithila Developers in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900012009. It was launched in September 2017. It has 64 units in 1 building: 62 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 31 are for sale and 33 are rehab units for existing members.
Its registered possession date is April 2029, extended by 7 years 4 months from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
0 units booked out of 31 units for sale (0%). Since the July 2026 update, the possession date has moved from December 2022 to April 2029.