Nemat -E- Farooque Heritage, Mumbai Central

by Falakdeveloper · Mumbai Central, Mumbai 400008 · Map

Launched
Sep 20171 yr 9 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 7 yrs 10 mths
Concrete structure
70%Mid-construction
Booked
–
Buildings
10.1 acres
MahaRERA complaints
11Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
72
Total units
72
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%98
100%70%0%–
100%70%0%–
100%70%0%98

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400008

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400008
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 9 mths4 yrs 10 mths
Possession date extendedBy 7 yrs 10 mths4 of 4
Possession date (MahaRERA)Apr 2027Oct 2028
Concrete structure (RCC)70%68%
Units booked–40%
MahaRERA complaints (filed by or against the builder)112

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Nemat -E- Farooque Heritage by Falakdeveloper is a 72-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in September 2017 with possession due in April 2027. The concrete structure (RCC) is 70% complete.

Read full summary

Nemat -E- Farooque Heritage is a BMC-sanctioned project by Falakdeveloper in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900013072. It was launched in September 2017. It has 72 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 7 years 10 months from the original June 2019. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.