Ekdant, Mumbai Central

Ready to moveLapsed

by Zenia Realty · Mumbai Central, Mumbai 400008 · Map

Launched
Aug 20176 yrs 11 mths promised
Possession (MahaRERA)
Jul 2024Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
61
2 BHK
1
Total units
62
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%–
100%100%90%–
100%100%90%44

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400008

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400008
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 11 mths4 yrs 10 mths
Possession date extendedNo6 of 6
Possession date (MahaRERA)Jul 2024Apr 2027
Concrete structure (RCC)100%34%
Units booked–22%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ekdant by Zenia Realty is a 62-unit project in Mumbai Central, Mumbai 400008, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Ekdant is a project by Zenia Realty in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900007614. It was launched in August 2017. It has 62 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in July 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.