Shanta Durga, Mahim

Lapsed

by Nine Dimensions Housing LLP · Mahim, Mumbai 400016 · Map

Launched
Feb 20186 yrs 10 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked (free sale)
42 of 42100% · 49 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale42 booked out of 42 units

Rehab49 units for existing members

Total 91 units. Rehab units are not for sale.

Project facts

1 RK
4
1 BHK
4
2 BHK
47
3 BHK
35
Other units
1
Total units
91
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
42
Rehab units
49

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%42
100%100%60%–
100%100%60%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400016

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400016
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 10 mths6 yrs 4 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)Dec 2024Jun 2024
Concrete structure (RCC)100%100%
Units booked (free sale)100%52%
MahaRERA complaints (filed by or against the builder)07

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Shanta Durga by Nine Dimensions Housing LLP is a 91-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in February 2018; its MahaRERA registration has lapsed. 42 units booked out of 42 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shanta Durga is a BMC-sanctioned project by Nine Dimensions Housing LLP in Mahim, Mumbai 400016, registered with MahaRERA as P51900015345. It was launched in February 2018. It has 91 units in 1 building: 90 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 91 units, 42 are for sale and 49 are rehab units for existing members.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

42 units booked out of 42 units for sale (100%).