- Launched
- Aug 20172 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jun 2024Extended by 4 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 30 of 9831%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 8Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 10
- 2 BHK
- 53
- 3 BHK
- 5
- Other units
- 30
- Total units
- 98
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 75% | 30 | |
| 100% | 100% | 75% | 30 | |
| 100% | 100% | 75% | 21 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400016
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 4 mths | 6 yrs 4 mths |
| Possession date extended | By 4 yrs 6 mths | 3 of 6 |
| Possession date (MahaRERA) | Jun 2024 | Feb 2025 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 31% | 73% |
| MahaRERA complaints (filed by or against the builder) | 8 | 0 |
The 6 projects
- Tridhaatu Kshitij, Mahim
- Shristi Sea View, Mahim
- Mehrabad, Mahim
- Shree Sai Mauli, Mahim
- Mama Heights, Mahim
- Shanta Durga, Mahim
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Tridhaatu Kshitij | August 2017 | December 2023 | 100% | 34 units booked out of total 66 units |
| Shristi Sea View | August 2017 | December 2023 | 66% | 37 units booked out of total 49 units |
| Mehrabad | August 2017 | December 2025 | 100% | 14 units booked out of total 48 units |
| Shree Sai Mauli | August 2017 | December 2027 | 60% | 10 units booked out of 12 units for sale |
| Mama Heights | July 2017 | April 2025 | 100% | 51 units booked out of 72 units for sale |
| Shanta Durga | February 2018 | December 2024 | 100% | 42 units booked out of 42 units for sale |
About this project
Ruparel Iris by Ruparel Estates India Pvt Ltd is a 98-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in August 2017; its MahaRERA registration has lapsed. 30 units booked out of total 98 units. The concrete structure (RCC) is complete.
Read full summary
Ruparel Iris is a BMC-sanctioned project by Ruparel Estates India Pvt Ltd in Mahim, Mumbai 400016, registered with MahaRERA as P51900005988. It was launched in August 2017. It has 98 units in 1 building: 68 homes (1, 2 and 3 BHK) and 30 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2024, after an extension of 4 years 6 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.
30 units booked out of total 98 units (31%).
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.