Skip to main content

Ruparel NOVA, Parel

Ready to moveLapsed

by Shree Sukhakarta Developers PvtLtd · Parel, Mumbai 400012 · Map

Launched
Mar 20195 yrs 9 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
160 of 16597%
Buildings
12.6 acres
MahaRERA complaints
19Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
165
Total units
165
Buildings
1
Land
2.6 acres
Phases
1
MahaRERA complaints
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jul 2026Oct 2026Dec 2024: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%160
100%100%95%160
0%0%0%75

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ruparel NOVA by Shree Sukhakarta Developers PvtLtd (Ruparel) is a 165-unit SRA-sanctioned project in Parel, Mumbai 400012, launched in March 2019; its MahaRERA registration has lapsed. 160 units booked out of total 165 units. The concrete structure (RCC) is complete.

Read full summary

Ruparel NOVA is an SRA-sanctioned project by Shree Sukhakarta Developers PvtLtd in Parel, Mumbai 400012, registered with MahaRERA as P51900019946. It was launched in March 2019. It has 165 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

160 units booked out of total 165 units (97%).

Ruparel's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA28
Total units across these projects6,570
Completed without extending the possession date0
Completed after an extension1
Lapsed12
Under construction15
Possession date extended on the builder's application14
Typical time from launch to 100% structure5 years 9 months
MahaRERA complaints (filed by or against the builder), all Ruparel projects872 (22 of 28 projects)

See all Ruparel projects →