Ark Blue Waves, Dadar West

Ready to moveLapsed

by Sneha Realty Private Limited · Dadar West, Mumbai 400028 · Map

Launched
Jun 20195 yrs 1 mth originally promised
Possession (MahaRERA)
Jun 2025Extended by 11 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
13 of 4032%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
4
2 BHK
22
3 BHK
2
Other units
12
Total units
40
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%13
100%100%95%–
100%100%95%–
100%100%95%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400028

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 1 mth3 yrs 11 mths
Possession date extendedBy 11 mths3 of 4
Possession date (MahaRERA)Jun 2025Jul 2025
Concrete structure (RCC)100%60%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Ark Blue Waves by Sneha Realty Private Limited is a 40-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in June 2019; its MahaRERA registration has lapsed. 13 units booked out of total 40 units. The concrete structure (RCC) is complete.

Read full summary

Ark Blue Waves is a BMC-sanctioned project by Sneha Realty Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as P51900021267. It was launched in June 2019. It has 40 units in 1 building: 28 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 11 months from the original July 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

13 units booked out of total 40 units (32%).