Ave Maria Apartment, Dadar West

Ready to moveLapsed

by Suraj Estate Developers Ltd · Dadar West, Mumbai 400028 · Map

Launched
Aug 20195 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
18
2 BHK
21
Total units
39
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 98%Dec 2025: Final finishes 98%Jul 2026: Final finishes 98%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%175
100%100%98%–
100%100%98%–
100%100%98%175

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400028

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths3 yrs 11 mths
Possession date extendedBy 1 yr3 of 4
Possession date (MahaRERA)Dec 2025May 2025
Concrete structure (RCC)100%60%
Units booked–75%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Ave Maria Apartment by Suraj Estate Developers Ltd is a 39-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in August 2019; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Ave Maria Apartment is a BMC-sanctioned project by Suraj Estate Developers Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as P51900021954. It was launched in August 2019. It has 39 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 1 year from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

Suraj Estate's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA17
Total units across these projects1,217
Completed without extending the possession date0
Completed after an extension4
Lapsed3
Under construction10
Possession date extended on the builder's application10
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Suraj Estate projects11 (6 of 17 projects)