Marathon Futurex, Lower Parel
Ready to moveLapsed
by Marathon Realty Pvt Ltd · Lower Parel, Mumbai 400013 · Map
- Launched
- Jun 2020First of 2 phases
- Possession (MahaRERA)
- Jun 2022 – Dec 2023Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 95
- Total units
- 95
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Marathon Futurex 2 Ready to move Lapsed | P51900025477 | 0 | 100% | – | |
| Marathon Futurex 3 Mid-construction Lapsed | P51900033535 | 0 | 97% | – |
Show updates by phase
Marathon Futurex 2 (P51900025477)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 23 |
"–" means MahaRERA shows no figure for that update.
Marathon Futurex 3 (P51900033535)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 90% | – | |
| 100% | 97% | 90% | – | |
| 100% | 97% | 90% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Marathon Futurex by Marathon Realty Pvt Ltd is a 95-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, registered with MahaRERA in 2 phases, with possession dates from June 2022 to December 2023. The concrete structure (RCC) is complete.
Read full summary
Marathon Futurex is a BMC-sanctioned project by Marathon Realty Pvt Ltd in Lower Parel, Mumbai 400013, registered with MahaRERA as 2 phases (P51900025477, P51900033535). The first phase was launched in June 2020. Together the phases have 95 units in 2 buildings, as registered with MahaRERA. Both phases are lapsed on MahaRERA.
The phases' registered possession dates run from June 2022 to December 2023; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 90% complete. Neither phase has its structure complete.
Marathon's track record in Mumbai
MahaRERA projects registered 2017–2024 in Mumbai
| Projects registered with MahaRERA | 11 |
|---|---|
| Total units across these projects | 818 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 2 |
| Lapsed | 6 |
| Under construction | 3 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 4 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Marathon projects | 11 (5 of 11 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.