Marathon Futurex, Lower Parel

Ready to moveLapsed

by Marathon Realty Pvt Ltd · Lower Parel, Mumbai 400013 · Map

Launched
Jun 2020First of 2 phases
Possession (MahaRERA)
Jun 2022 – Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
100%Weighted across 2 phases
Booked
–
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
95
Total units
95
Buildings
2
Land
0.5 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Marathon Futurex 2
Ready to move Lapsed
P519000254770100%–
Marathon Futurex 3
Mid-construction Lapsed
P51900033535097%–
Show updates by phase

Marathon Futurex 2 (P51900025477)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%–
100%100%90%–
100%100%90%23

"–" means MahaRERA shows no figure for that update.

Marathon Futurex 3 (P51900033535)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%90%–
100%97%90%–
100%97%90%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

How to read construction stages

About this project

Marathon Futurex by Marathon Realty Pvt Ltd is a 95-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, registered with MahaRERA in 2 phases, with possession dates from June 2022 to December 2023. The concrete structure (RCC) is complete.

Read full summary

Marathon Futurex is a BMC-sanctioned project by Marathon Realty Pvt Ltd in Lower Parel, Mumbai 400013, registered with MahaRERA as 2 phases (P51900025477, P51900033535). The first phase was launched in June 2020. Together the phases have 95 units in 2 buildings, as registered with MahaRERA. Both phases are lapsed on MahaRERA.

The phases' registered possession dates run from June 2022 to December 2023; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 90% complete. Neither phase has its structure complete.

Marathon's track record in Mumbai

MahaRERA projects registered 2017–2024 in Mumbai

Projects registered with MahaRERA11
Total units across these projects818
Completed without extending the possession date0
Completed after an extension2
Lapsed6
Under construction3
Possession date extended on the builder's application5
Typical time from launch to 100% structure4 years 6 months
MahaRERA complaints (filed by or against the builder), all Marathon projects11 (5 of 11 projects)

See all Marathon projects →