Raheja Modern Vivarea South Tower, Mahalaxmi

by K Raheja Corp Real Estate Private Limited · Mahalaxmi, Mumbai 400011 · Map

Launched
Mar 20226 yrs 6 mths promised
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
100%Nearing possession
Booked
142 of 15293% · 136 in Jul 2026
Buildings
13.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
70
4 BHK
70
5+ BHK
12
Total units
152
Buildings
1
Land
3.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 98%Jul 2026: Concrete structure (RCC) 98%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 13%Dec 2025: Final finishes 49%Jul 2026: Final finishes 49%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%142
100%98%49%136
100%98%49%128
100%50%13%98

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400011

Projects with 70–350 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400011
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 6 mths4 yrs 3 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)Sep 2028Dec 2026
Concrete structure (RCC)100%95%
Units booked93%59%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Raheja Modern Vivarea South Tower by K Raheja Corp Real Estate Private Limited is a 152-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in March 2022 with possession due in September 2028. 142 units booked out of total 152 units. The concrete structure (RCC) is complete.

Read full summary

Raheja Modern Vivarea South Tower is a BMC-sanctioned project by K Raheja Corp Real Estate Private Limited in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900034288. It was launched in March 2022. It has 152 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

142 units booked out of total 152 units (93%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 98% to 100%.

K Raheja Corp's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA12
Total units across these projects1,377
Completed without extending the possession date3
Completed after an extension1
Lapsed0
Under construction8
Possession date extended on the builder's application1
Typical time from launch to 100% structure4 years 4 months
MahaRERA complaints (filed by or against the builder), all K Raheja Corp projects3 (3 of 12 projects)

See all K Raheja Corp projects →