Bismillah Tower, Mahalaxmi
Ready to move
by Hayat Ahmed Asir Ahmed Ansari · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Mar 20214 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr 6 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 18 of 2864% · 65 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale18 booked out of 28 units
Rehab65 units for existing members
Total 93 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 89
- Other units
- 4
- Total units
- 93
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 28
- Rehab units
- 65
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 18 | |
| 100% | 100% | 100% | 18 | |
| 100% | 100% | 86% | 18 | |
| 100% | 100% | 85% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400011
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 6 yrs |
| Possession date extended | By 1 yr 6 mths | 0 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Mar 2028 |
| Concrete structure (RCC) | 100% | 95% |
| Units booked (free sale) | 64% | 93% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Redevelopment of Gomtibai Chawl, Mahalaxmi
- Raheja Modern Vivarea North Tower, Mahalaxmi
- Raheja Modern Vivarea South Tower, Mahalaxmi
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Redevelopment of Gomtibai Chawl | May 2021 | June 2026 | 95% | 24 units booked out of 41 units for sale |
| Raheja Modern Vivarea North Tower | March 2022 | March 2028 | 88% | 114 units booked out of total 114 units |
| Raheja Modern Vivarea South Tower | March 2022 | September 2028 | 100% | 142 units booked out of total 152 units |
About this project
Bismillah Tower by Hayat Ahmed Asir Ahmed Ansari is a 93-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in March 2021 with possession due in December 2026. 18 units booked out of 28 units for sale. The concrete structure (RCC) is complete.
Read full summary
Bismillah Tower is a BMC-sanctioned project by Hayat Ahmed Asir Ahmed Ansari in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900028695. It was launched in March 2021. It has 93 units in 1 building: 89 homes (1 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 93 units, 28 are for sale and 65 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year 6 months from the original June 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
18 units booked out of 28 units for sale (64%).