Redevelopment of Gomtibai Chawl, Mahalaxmi
Lapsed
by Silverline Enterprises · Mahalaxmi, Mumbai 400011 · Map
- Launched
- May 20215 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 24 of 4159% · 64 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale24 booked out of 41 units
Rehab64 units for existing members
Total 105 units. Rehab units are not for sale.
Project facts
- 1 RK
- 17
- 1 BHK
- 47
- 2 BHK
- 23
- 3 BHK
- 2
- Other units
- 16
- Total units
- 105
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 41
- Rehab units
- 64
- Reserved units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 15% | 24 | |
| 100% | 46% | 0% | 24 | |
| 100% | 46% | 0% | 24 | |
| 100% | 46% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400011
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 1 mth | 6 yrs |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Jun 2026 | Mar 2028 |
| Concrete structure (RCC) | 95% | 100% |
| Units booked (free sale) | 59% | 93% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Bismillah Tower, Mahalaxmi
- Raheja Modern Vivarea North Tower, Mahalaxmi
- Raheja Modern Vivarea South Tower, Mahalaxmi
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bismillah Tower | March 2021 | December 2026 | 100% | 18 units booked out of 28 units for sale |
| Raheja Modern Vivarea North Tower | March 2022 | March 2028 | 88% | 114 units booked out of total 114 units |
| Raheja Modern Vivarea South Tower | March 2022 | September 2028 | 100% | 142 units booked out of total 152 units |
About this project
Redevelopment of Gomtibai Chawl by Silverline Enterprises is a 105-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in May 2021; its MahaRERA registration has lapsed. 24 units booked out of 41 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Redevelopment of Gomtibai Chawl is a BMC-sanctioned project by Silverline Enterprises in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900029209. It was launched in May 2021. It has 105 units in 1 building: 89 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 105 units, 41 are for sale and 64 are rehab units for existing members.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 15% complete.
24 units booked out of 41 units for sale (59%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 46% to 95%.