Raheja Modern Vivarea North Tower, Mahalaxmi
by K Raheja Corp Real Estate Private Limited · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Mar 20226 yrs promised
- Possession (MahaRERA)
- Mar 2028Not extended
- Concrete structure
- 88%Mid-construction
- Booked
- 114 of 114100%
- Buildings
- 13.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 114
- Total units
- 114
- Buildings
- 1
- Land
- 3.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 88% | 50% | 114 | |
| 0% | 0% | 0% | 114 | |
| 0% | 0% | 0% | – | |
| 100% | 88% | 50% | 95 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400011
Projects with 50–250 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs | 4 yrs 3 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Mar 2028 | Dec 2026 |
| Concrete structure (RCC) | 88% | 95% |
| Units booked | 100% | 59% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Viva, Mahalaxmi
- Redevelopment of Gomtibai Chawl, Mahalaxmi
- Bismillah Tower, Mahalaxmi
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Viva | November 2022 | June 2027 | 77% | 30 units booked out of 72 units for sale |
| Redevelopment of Gomtibai Chawl | May 2021 | June 2026 | 95% | 24 units booked out of 41 units for sale |
| Bismillah Tower | March 2021 | December 2026 | 100% | 18 units booked out of 28 units for sale |
About this project
Raheja Modern Vivarea North Tower by K Raheja Corp Real Estate Private Limited is a 114-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in March 2022 with possession due in March 2028. 114 units booked out of total 114 units. The concrete structure (RCC) is 88% complete.
Read full summary
Raheja Modern Vivarea North Tower is a BMC-sanctioned project by K Raheja Corp Real Estate Private Limited in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900034289. It was launched in March 2022. It has 114 units in 1 building, with 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 88% complete, final finishes 50% complete.
114 units booked out of total 114 units (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 88%.
K Raheja Corp's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 1,377 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 8 |
| Possession date extended on the builder's application | 1 |
| Typical time from launch to 100% structure | 4 years 4 months |
| MahaRERA complaints (filed by or against the builder), all K Raheja Corp projects | 3 (3 of 12 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.