Aadi Arpan, Sion
by Aadi Shikhar LLP · Sion, Mumbai 400022 · Map
- Launched
- Feb 20232 yrs 5 mths originally promised
- Possession (MahaRERA)
- Jul 2026Extended by 1 yr
- Concrete structure
- 97%Mid-construction
- Booked (free sale)
- 6 of 1443% · 28 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 14 units
Rehab28 units for existing members
Land-owner share2 units, not for sale
Total 44 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 15
- 2 BHK
- 4
- 3 BHK
- 22
- 5+ BHK
- 1
- Other units
- 2
- Total units
- 44
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 14
- Rehab units
- 28
- Land-owner share (not for sale)
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 45% | 6 | |
| 100% | 97% | 45% | 6 | |
| 100% | 89% | 0% | 6 | |
| 100% | 52% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400022
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 2 yrs 8 mths |
| Possession date extended | By 1 yr | 2 of 4 |
| Possession date (MahaRERA) | Jul 2026 | Jan 2027 |
| Concrete structure (RCC) | 97% | 80% |
| Units booked (free sale) | 43% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Pinnacle, Sion
- The IVY, Sion
- Pr Heights, Sion
- Lodha Matunga, Sion
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pinnacle | February 2023 | March 2027 | 90% | 31 units booked out of total 58 units |
| The IVY | January 2023 | December 2026 | 17% | 9 units booked out of 24 units for sale |
| Pr Heights | May 2023 | March 2025 | 100% | 14 units booked out of 15 units for sale |
| Lodha Matunga | August 2023 | April 2028 | 70% | 47 units booked out of total 58 units |
About this project
Aadi Arpan by Aadi Shikhar LLP is a 44-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in February 2023 with possession due in July 2026. 6 units booked out of 14 units for sale. The concrete structure (RCC) is 97% complete.
Read full summary
Aadi Arpan is a BMC-sanctioned project by Aadi Shikhar LLP in Sion, Mumbai 400022, registered with MahaRERA as P51900049501. It was launched in February 2023. It has 44 units in 1 building: 42 homes (1, 2, 3 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 14 are for sale, 28 are rehab units for existing members and 2 are the land-owner's share, not for sale.
Possession was due in July 2026, after an extension of 1 year from the original July 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 97% complete, final finishes 45% complete.
6 units booked out of 14 units for sale (43%).