Skip to main content

Lodha Matunga, Sion

by Lodha Developers Limited · Sion, Mumbai 400022 · Map

Launched
Aug 20234 yrs 8 mths promised
Possession (MahaRERA)
Apr 2028Not extended
Concrete structure
70%Mid-construction
Booked
47 of 5881%
Buildings
11.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
25
4 BHK
31
5+ BHK
2
Total units
58
Buildings
1
Land
1.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 1%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%47
100%70%0%47
100%70%0%47
100%1%0%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400022

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400022
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 8 mths2 yrs 5 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)Apr 2028Jul 2026
Concrete structure (RCC)70%97%
Units booked81%53%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Lodha Matunga by Lodha Developers Limited is a 58-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in August 2023 with possession due in April 2028. 47 units booked out of total 58 units. The concrete structure (RCC) is 70% complete.

Read full summary

Lodha Matunga is a BMC-sanctioned project by Lodha Developers Limited in Sion, Mumbai 400022, registered with MahaRERA as P51900052415. It was launched in August 2023. It has 58 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.

47 units booked out of total 58 units (81%).

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →