Lodha Matunga, Sion
by Lodha Developers Limited · Sion, Mumbai 400022 · Map
- Launched
- Aug 20234 yrs 8 mths promised
- Possession (MahaRERA)
- Apr 2028Not extended
- Concrete structure
- 70%Mid-construction
- Booked
- 47 of 5881%
- Buildings
- 11.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 25
- 4 BHK
- 31
- 5+ BHK
- 2
- Total units
- 58
- Buildings
- 1
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 47 | |
| 100% | 70% | 0% | 47 | |
| 100% | 70% | 0% | 47 | |
| 100% | 1% | 0% | 22 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400022
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 2 yrs 5 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Apr 2028 | Jul 2026 |
| Concrete structure (RCC) | 70% | 97% |
| Units booked | 81% | 53% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Pr Heights, Sion
- Pinnacle, Sion
- Aadi Arpan, Sion
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pr Heights | May 2023 | March 2025 | 100% | 14 units booked out of 15 units for sale |
| Pinnacle | February 2023 | March 2027 | 90% | 31 units booked out of total 58 units |
| Aadi Arpan | February 2023 | July 2026 | 97% | 6 units booked out of 14 units for sale |
About this project
Lodha Matunga by Lodha Developers Limited is a 58-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in August 2023 with possession due in April 2028. 47 units booked out of total 58 units. The concrete structure (RCC) is 70% complete.
Read full summary
Lodha Matunga is a BMC-sanctioned project by Lodha Developers Limited in Sion, Mumbai 400022, registered with MahaRERA as P51900052415. It was launched in August 2023. It has 58 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
47 units booked out of total 58 units (81%).
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.