Pr Heights, Sion

Lapsed

by Pankhi Reliable Developers LLP · Sion, Mumbai 400022 · Map

Launched
May 20231 yr 10 mths promised
Possession (MahaRERA)
Mar 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked (free sale)
14 of 1593% · 13 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 15 units

Rehab13 units for existing members

Total 28 units. Rehab units are not for sale.

Project facts

1 RK
13
1 BHK
13
2 BHK
1
Other units
1
Total units
28
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 40%Dec 2025: Final finishes 40%Jul 2026: Final finishes 40%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 100%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%14
100%100%40%14
100%100%40%14
100%100%40%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400022

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400022
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 10 mths2 yrs 8 mths
Possession date extendedNo3 of 4
Possession date (MahaRERA)Mar 2025Jan 2027
Concrete structure (RCC)100%80%
Units booked (free sale)93%48%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Pr Heights by Pankhi Reliable Developers LLP is a 28-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in May 2023; its MahaRERA registration has lapsed. 14 units booked out of 15 units for sale. The concrete structure (RCC) is complete.

Read full summary

Pr Heights is a BMC-sanctioned project by Pankhi Reliable Developers LLP in Sion, Mumbai 400022, registered with MahaRERA as P51800050926. It was launched in May 2023. It has 28 units in 1 building: 27 homes (1 RK, 1 BHK and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 28 units, 15 are for sale and 13 are rehab units for existing members.

Possession was due in March 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.

14 units booked out of 15 units for sale (93%).