Montesouth Pilatus 4, Mahalaxmi
by Swayam Realtors & Traders LLP · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Feb 20234 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 20
- 3 BHK
- 39
- Total units
- 59
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400011
Projects with 20–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 10 mths | 3 yrs 3 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Oct 2027 |
| Concrete structure (RCC) | 0% | 35% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Mahanagar Heights, Mahalaxmi
- Viva, Mahalaxmi
- Park Crown, Mahalaxmi
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mahanagar Heights | March 2023 | October 2027 | 35% | 18 units booked out of 70 units for sale |
| Viva | November 2022 | June 2027 | 77% | 30 units booked out of 72 units for sale |
| Park Crown | November 2023 | December 2028 | 23% | – |
About this project
Montesouth Pilatus 4 by Swayam Realtors & Traders LLP is a 59-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in February 2023 with possession due in December 2027. Work on the concrete structure (RCC) has not started.
Read full summary
Montesouth Pilatus 4 is a BMC-sanctioned project by Swayam Realtors & Traders LLP in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900049688. It was launched in February 2023. It has 59 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.