Park Crown, Mahalaxmi

by Ss Crown Infrastructure · Mahalaxmi, Mumbai 400011 · Map

Launched
Nov 20235 yrs 1 mth promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
23%Mid-construction
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
99
Total units
99
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)23%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 0%Dec 2024: Concrete structure (RCC) 23%Dec 2025: Concrete structure (RCC) 23%Jul 2026: Concrete structure (RCC) 23%Oct 2026: Concrete structure (RCC) 23%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Concrete structure (RCC) 23%Excavation 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%23%0%–
0%23%0%–
0%23%0%–
0%23%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400011

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400011
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 1 mth3 yrs 3 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)Dec 2028Oct 2027
Concrete structure (RCC)23%35%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Park Crown by Ss Crown Infrastructure is a 99-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in November 2023 with possession due in December 2028. The concrete structure (RCC) is 23% complete.

Read full summary

Park Crown is a BMC-sanctioned project by Ss Crown Infrastructure in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900053737. It was launched in November 2023. It has 99 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation not started, structure (RCC) 23% complete, final finishes not started.