Mahanagar Heights, Mahalaxmi

by Mahanagar Construction Private Limited · Mahalaxmi, Mumbai 400011 · Map

Launched
Mar 20233 yrs 3 mths originally promised
Possession (MahaRERA)
Oct 2027Extended by 1 yr 4 mths
Concrete structure
35%Mid-construction
Booked (free sale)
18 of 7026% · 1 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale18 booked out of 70 units

Rehab1 unit for existing members

Total 71 units. Rehab units are not for sale.

Project facts

1 BHK
20
2 BHK
51
Total units
71
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
70
Rehab units
1
Reserved units
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 50%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 35%Oct 2026: Concrete structure (RCC) 35%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%18
100%35%0%18
50%0%0%12
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400011

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400011
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths4 yrs 10 mths
Possession date extendedBy 1 yr 4 mths1 of 3
Possession date (MahaRERA)Oct 2027Dec 2027
Concrete structure (RCC)35%23%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Mahanagar Heights by Mahanagar Construction Private Limited is a 71-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in March 2023 with possession due in October 2027. 18 units booked out of 70 units for sale. The concrete structure (RCC) is 35% complete.

Read full summary

Mahanagar Heights is a BMC-sanctioned project by Mahanagar Construction Private Limited in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900049886. It was launched in March 2023. It has 71 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 71 units, 70 are for sale and 1 is a rehab unit for existing members.

Its registered possession date is October 2027, extended by 1 year 4 months from the original June 2026. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.

18 units booked out of 70 units for sale (26%).