Kinjal Pride, Parel
by Hi Rock Construction Pvt Ltd · Parel, Mumbai 400012 · Map
- Launched
- Oct 20233 yrs promised
- Possession (MahaRERA)
- Oct 2026Not extended
- Concrete structure
- 59%Mid-construction
- Booked (free sale)
- 27 of 27100% · 46 rehab units
- Buildings
- 20.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale27 booked out of 27 units
Rehab46 units for existing members
Total 73 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 35
- 2 BHK
- 33
- Other units
- 5
- Total units
- 73
- Buildings
- 2
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 27
- Rehab units
- 46
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 59% | 0% | 27 | |
| 100% | 18% | 0% | 27 | |
| 100% | 18% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400012
Projects with 30–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 4 yrs 7 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Oct 2026 | Sep 2028 |
| Concrete structure (RCC) | 59% | 20% |
| Units booked (free sale) | 100% | 54% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Evana Heights, Parel
- Bhoiwada Chandra Bhuvan CHS Ltd, Parel
- Arham Imperia, Parel
- Avanta Heights, Parel
- Nirban Avenue 1, Parel
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Evana Heights | October 2023 | September 2028 | 65% | 74 units booked out of total 82 units |
| Bhoiwada Chandra Bhuvan CHS Ltd | December 2023 | December 2026 | 0% | – |
| Arham Imperia | May 2023 | April 2029 | 0% | 25 units booked out of total 135 units |
| Avanta Heights | April 2024 | June 2027 | 90% | 33 units booked out of 40 units for sale |
| Nirban Avenue 1 | May 2024 | December 2028 | 20% | 7 units booked out of 27 units for sale |
About this project
Kinjal Pride by Hi Rock Construction Pvt Ltd is a 73-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in October 2023 with possession due in October 2026. 27 units booked out of 27 units for sale. The concrete structure (RCC) is 59% complete.
Read full summary
Kinjal Pride is a BMC-sanctioned project by Hi Rock Construction Pvt Ltd in Parel, Mumbai 400012, registered with MahaRERA as P51900052854. It was launched in October 2023. It has 73 units in 2 buildings: 68 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 73 units, 27 are for sale and 46 are rehab units for existing members.
Its registered possession date is October 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 59% complete, final finishes not started.
27 units booked out of 27 units for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 18% to 59%.