by Nirban Housing And Development LLP · Parel, Mumbai 400012 · Map

Launched
May 20244 yrs 7 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
20%Mid-construction
Booked (free sale)
7 of 2726% · 49 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 27 units

Rehab49 units for existing members

Total 76 units. Rehab units are not for sale.

Project facts

1 BHK
62
Other units
14
Total units
76
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
27
Rehab units
49

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)20%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 10%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 20%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 20%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%7
100%0%0%0
100%0%0%0
10%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400012

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400012
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 7 mths3 yrs
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2028Dec 2026
Concrete structure (RCC)20%59%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Nirban Avenue 1 by Nirban Housing And Development LLP is a 76-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in May 2024 with possession due in December 2028. 7 units booked out of 27 units for sale. The concrete structure (RCC) is 20% complete.

Read full summary

Nirban Avenue 1 is a BMC-sanctioned project by Nirban Housing And Development LLP in Parel, Mumbai 400012, registered with MahaRERA as P51900056382. It was launched in May 2024. It has 76 units in 1 building: 62 homes (1 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 76 units, 27 are for sale and 49 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.

7 units booked out of 27 units for sale (26%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 20%.