Tulsi Heritage, Dadar East

by Blue Stone Developers LLP · Dadar East, Mumbai 400014 · Map

Launched
Jun 20244 yrs 3 mths promised
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
10%Mid-construction
Booked (free sale)
15 of 2268% · 16 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale15 booked out of 22 units

Rehab16 units for existing members

Total 38 units. Rehab units are not for sale.

Project facts

1 BHK
16
2 BHK
18
3 BHK
3
Other units
1
Total units
38
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
22
Rehab units
16
Reserved units
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)10%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 76%Oct 2026: Concrete structure (RCC) 10%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 10%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%10%15
100%76%10%15
100%10%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400014

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400014
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths4 yrs 2 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Sep 2028Sep 2028
Concrete structure (RCC)10%86%
Units booked (free sale)68%67%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Tulsi Heritage by Blue Stone Developers LLP is a 38-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in June 2024 with possession due in September 2028. 15 units booked out of 22 units for sale. The concrete structure (RCC) is 10% complete.

Read full summary

Tulsi Heritage is a BMC-sanctioned project by Blue Stone Developers LLP in Dadar East, Mumbai 400014, registered with MahaRERA as P51900066485. It was launched in June 2024. It has 38 units in 1 building: 37 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 22 are for sale and 16 are rehab units for existing members.

Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 10% complete, final finishes 10% complete.

15 units booked out of 22 units for sale (68%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 76% to 10%.