Sugee Srushti, Dadar East

by Sugee Fifteen Developers LLP · Dadar East, Mumbai 400014 · Map

Launched
Jul 20243 yrs 3 mths promised
Possession (MahaRERA)
Oct 2027Not extended
Concrete structure
83%Mid-construction
Booked
12 of 1867% · 11 in Jul 2026
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
18
Total units
18
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)83%
Finishes, lifts and services5%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 78%Oct 2026: Concrete structure (RCC) 83%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 5%Excavation 100%Concrete structure (RCC) 83%Final finishes 5%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%83%5%12
100%78%0%11
100%0%0%1
100%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400014

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400014
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths4 yrs 6 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Oct 2027Jan 2029
Concrete structure (RCC)83%52%
Units booked67%69%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Sugee Srushti by Sugee Fifteen Developers LLP is an 18-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in July 2024 with possession due in October 2027. 12 units booked out of total 18 units. The concrete structure (RCC) is 83% complete.

Read full summary

Sugee Srushti is a BMC-sanctioned project by Sugee Fifteen Developers LLP in Dadar East, Mumbai 400014, registered with MahaRERA as P51900077195. It was launched in July 2024. It has 18 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 83% complete, final finishes 5% complete.

12 units booked out of total 18 units (67%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 78% to 83%.