Shree Niwas, Dadar East
by Endemic Properties LLP · Dadar East, Mumbai 400014 · Map
- Launched
- Oct 20244 yrs 8 mths promised
- Possession (MahaRERA)
- Jun 2029Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 9 of 1369% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 13 units
Rehab8 units for existing members
Land-owner share1 unit, not for sale
Total 22 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 11
- 3 BHK
- 2
- 4 BHK
- 6
- Other units
- 2
- Total units
- 22
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 8
- Land-owner share (not for sale)
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 25% | 9 | |
| 100% | 100% | 25% | 9 | |
| 100% | 40% | 0% | 9 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400014
Projects with 10–40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 3 yrs 9 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Jun 2029 | Sep 2028 |
| Concrete structure (RCC) | 100% | 31% |
| Units booked (free sale) | 69% | 56% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Sanghvi Optima, Dadar East
- Sugee Srushti, Dadar East
- Tulsi Heritage, Dadar East
- Siddhgiri, Dadar East
- Ekta Vistabella, Dadar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sanghvi Optima | August 2024 | May 2028 | 0% | – |
| Sugee Srushti | July 2024 | October 2027 | 83% | 12 units booked out of total 18 units |
| Tulsi Heritage | June 2024 | September 2028 | 10% | 15 units booked out of 22 units for sale |
| Siddhgiri | March 2025 | December 2028 | 70% | 4 units booked out of 9 units for sale |
| Ekta Vistabella | March 2025 | December 2028 | 31% | 3 units booked out of 16 units for sale |
About this project
Shree Niwas by Endemic Properties LLP is a 22-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in October 2024 with possession due in June 2029. 9 units booked out of 13 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shree Niwas is a BMC-sanctioned project by Endemic Properties LLP in Dadar East, Mumbai 400014, registered with MahaRERA as P51900077703. It was launched in October 2024. It has 22 units in 1 building: 20 homes (1, 2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 13 are for sale, 8 are rehab units for existing members and 1 is the land-owner's share, not for sale.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.
9 units booked out of 13 units for sale (69%).