Suraj Aureva, Dadar West
by Suraj Estate Developers Ltd · Dadar West, Mumbai 400028 · Map
- Launched
- Jul 20256 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2031Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 19 of 2673% · 28 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale19 booked out of 26 units
Rehab28 units for existing members
Land-owner share4 units, not for sale
Total 58 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 35
- 2 BHK
- 17
- Other units
- 6
- Total units
- 58
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 26
- Rehab units
- 28
- Land-owner share (not for sale)
- 4
- Reserved units
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 19 | |
| 80% | 0% | 0% | 22 | |
| 10% | 0% | 0% | 22 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400028
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 5 mths | 3 yrs 1 mth |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2031 | Sep 2028 |
| Concrete structure (RCC) | 0% | 19% |
| Units booked (free sale) | 73% | 17% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Dipti Opal Bay, Dadar West
- Saffron, Dadar West
- Adityaraj Midtown, Dadar West
- Harsh Kusum Residence, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dipti Opal Bay | August 2025 | December 2029 | 20% | 0 units booked out of 15 units for sale |
| Saffron | June 2025 | December 2028 | 0% | 6 units booked out of 18 units for sale |
| Adityaraj Midtown | October 2025 | June 2028 | 18% | 5 units booked out of 29 units for sale |
| Harsh Kusum Residence | January 2025 | June 2025 | 80% | – |
About this project
Suraj Aureva by Suraj Estate Developers Ltd is a 58-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in July 2025 with possession due in December 2031. 19 units booked out of 26 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Suraj Aureva is a BMC-sanctioned project by Suraj Estate Developers Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as PM1170002500261. It was launched in July 2025. It has 58 units in 1 building: 52 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 58 units, 26 are for sale, 28 are rehab units for existing members and 4 are the land-owner's share, not for sale.
Its registered possession date is December 2031, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
19 units booked out of 26 units for sale (73%).
Suraj Estate's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 1,217 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 4 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 10 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Suraj Estate projects | 11 (6 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.