Suraj Aureva, Dadar West

by Suraj Estate Developers Ltd · Dadar West, Mumbai 400028 · Map

Launched
Jul 20256 yrs 5 mths promised
Possession (MahaRERA)
Dec 2031Not extended
Concrete structure
0%Early stage
Booked (free sale)
19 of 2673% · 28 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale19 booked out of 26 units

Rehab28 units for existing members

Land-owner share4 units, not for sale

Total 58 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
35
2 BHK
17
Other units
6
Total units
58
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
26
Rehab units
28
Land-owner share (not for sale)
4
Reserved units
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 10%Jul 2026: Excavation 80%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%19
80%0%0%22
10%0%0%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400028

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 5 mths3 yrs 1 mth
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2031Sep 2028
Concrete structure (RCC)0%19%
Units booked (free sale)73%17%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Suraj Aureva by Suraj Estate Developers Ltd is a 58-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in July 2025 with possession due in December 2031. 19 units booked out of 26 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Suraj Aureva is a BMC-sanctioned project by Suraj Estate Developers Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as PM1170002500261. It was launched in July 2025. It has 58 units in 1 building: 52 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 58 units, 26 are for sale, 28 are rehab units for existing members and 4 are the land-owner's share, not for sale.

Its registered possession date is December 2031, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

19 units booked out of 26 units for sale (73%).

Suraj Estate's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA17
Total units across these projects1,217
Completed without extending the possession date0
Completed after an extension4
Lapsed3
Under construction10
Possession date extended on the builder's application10
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Suraj Estate projects11 (6 of 17 projects)