Silicon Avenue, Mulund East

by Silicon Lifespaces LLP · Mulund East, Mumbai 400081 · Map

Launched
Sep 20243 yrs 3 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
11 of 6916% · 55 rehab units
Buildings
20.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 69 units

Rehab55 units for existing members

Total 124 units. Rehab units are not for sale.

Project facts

1 RK
5
1 BHK
22
2 BHK
79
3 BHK
11
Other units
7
Total units
124
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
69
Rehab units
55

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%11
0%0%0%0
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400081

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths4 yrs 1 mth
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2027Dec 2028
Concrete structure (RCC)0%0%
Units booked (free sale)16%66%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Silicon Avenue by Silicon Lifespaces LLP is a 124-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in September 2024 with possession due in December 2027. 11 units booked out of 69 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Silicon Avenue is a BMC-sanctioned project by Silicon Lifespaces LLP in Mulund East, Mumbai 400081, registered with MahaRERA as PM1180002400006. It was launched in September 2024. It has 124 units in 2 buildings: 117 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 124 units, 69 are for sale and 55 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

11 units booked out of 69 units for sale (16%). Since the July 2026 update, 11 more units have been booked.