HS Emerald, Mulund East

by HS Landmark LLP · Mulund East, Mumbai 400081 · Map

Launched
Mar 20253 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
72 of 11662% · 28 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale72 booked out of 116 units

Rehab28 units for existing members

Total 144 units. Rehab units are not for sale.

Project facts

1 RK
8
1 BHK
123
2 BHK
8
Other units
5
Total units
144
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
116
Rehab units
28

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%72
0%0%0%71
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400081

Projects with 60–300 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths4 yrs 1 mth
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2028Mar 2029
Concrete structure (RCC)0%0%
Units booked (free sale)62%48%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

HS Emerald by HS Landmark LLP is a 144-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in March 2025 with possession due in December 2028. 72 units booked out of 116 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

HS Emerald is an SRA-sanctioned project by HS Landmark LLP in Mulund East, Mumbai 400081, registered with MahaRERA as P51800079767. It was launched in March 2025. It has 144 units in 1 building: 139 homes (1 RK, 1 BHK and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 144 units, 116 are for sale and 28 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

72 units booked out of 116 units for sale (62%). Since the July 2026 update, 1 more unit has been booked.