Krishna Heights, Mulund East

by Sarvshubh Enterprises · Mulund East, Mumbai 400081 · Map

Launched
Jun 20253 yrs 6 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
25 of 5149% · 48 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 51 units

Rehab48 units for existing members

Total 99 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
26
2 BHK
45
3 BHK
2
Other units
25
Total units
99
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
51
Rehab units
48

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%25
100%50%0%18
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400081

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Sep 2029
Concrete structure (RCC)100%18%
Units booked (free sale)49%48%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Krishna Heights by Sarvshubh Enterprises is a 99-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in June 2025 with possession due in December 2028. 25 units booked out of 51 units for sale. The concrete structure (RCC) is complete.

Read full summary

Krishna Heights is a BMC-sanctioned project by Sarvshubh Enterprises in Mulund East, Mumbai 400081, registered with MahaRERA as PM1180002500085. It was launched in June 2025. It has 99 units in 1 building: 74 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 99 units, 51 are for sale and 48 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

25 units booked out of 51 units for sale (49%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 100%.