Oracle, Mulund East
by Hariom Realty · Mulund East, Mumbai 400081 · Map
- Launched
- Jul 20254 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 30%Mid-construction
- Booked (free sale)
- 55 of 7871% · 35 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale55 booked out of 78 units
Rehab35 units for existing members
Total 113 units. Rehab units are not for sale.
Project facts
- 1 RK
- 5
- 1 BHK
- 20
- 2 BHK
- 23
- 3 BHK
- 8
- Other units
- 57
- Total units
- 113
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 78
- Rehab units
- 35
- Reserved units
- 43
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 30% | 0% | 55 | |
| 100% | 0% | 0% | 51 | |
| 5% | 0% | 0% | 48 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400081
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 5 mths | 3 yrs 9 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Mar 2029 |
| Concrete structure (RCC) | 30% | 5% |
| Units booked (free sale) | 71% | 28% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Aria Skygardens, Mulund East
- Prem Arun, Mulund East
- HS Jewel, Mulund East
- Krishna Heights, Mulund East
- Bodhisatwa Ambedkar CHSL, Mulund East
- Signature Residences By C.K.V, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aria Skygardens | July 2025 | May 2030 | 0% | 1 unit booked out of total 46 units |
| Prem Arun | July 2025 | August 2028 | 5% | 3 units booked out of 15 units for sale |
| HS Jewel | June 2025 | June 2029 | 0% | 30 units booked out of 50 units for sale |
| Krishna Heights | June 2025 | December 2028 | 100% | 25 units booked out of 51 units for sale |
| Bodhisatwa Ambedkar CHSL | September 2025 | December 2027 | 77% | 0 units booked out of 22 units for sale |
| Signature Residences By C.K.V | September 2025 | December 2031 | 5% | 30 units booked out of total 82 units |
About this project
Oracle by Hariom Realty is a 113-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in July 2025 with possession due in December 2029. 55 units booked out of 78 units for sale. The concrete structure (RCC) is 30% complete.
Read full summary
Oracle is an SRA-sanctioned project by Hariom Realty in Mulund East, Mumbai 400081, registered with MahaRERA as PR1180002500319. It was launched in July 2025. It has 113 units in 1 building: 56 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 57 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 113 units, 78 are for sale and 35 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.
55 units booked out of 78 units for sale (71%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 30%.