Chaitanya, Borivali West
by Ovk Co-Operative Housing Society Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Oct 20252 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 0 of 30% · 30 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 3 units
Rehab30 units for existing members
Total 33 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 13
- 2 BHK
- 14
- 3 BHK
- 5
- Other units
- 1
- Total units
- 33
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 3
- Rehab units
- 30
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 0 | |
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 2 mths | 3 yrs 1 mth |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Nov 2028 |
| Concrete structure (RCC) | 90% | 40% |
| Units booked (free sale) | 0% | 57% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rishabraj Anuja, Borivali West
- New Aakanksha Chsl, Borivali West
- Jai Dena Chsl, Borivali West
- Avyukta Jayesh, Borivali West
- One Reserve, Borivali West
- Empire Eternity, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rishabraj Anuja | October 2025 | June 2028 | 100% | 4 units booked out of 5 units for sale |
| New Aakanksha Chsl | October 2025 | February 2028 | 70% | 8 units booked out of 12 units for sale |
| Jai Dena Chsl | October 2025 | December 2029 | 8% | 17 units booked out of 32 units for sale |
| Avyukta Jayesh | September 2025 | March 2029 | 10% | 10 units booked out of 20 units for sale |
| One Reserve | December 2025 | December 2030 | 0% | 14 units booked out of 23 units for sale |
| Empire Eternity | December 2025 | July 2028 | 80% | 7 units booked out of 16 units for sale |
About this project
Chaitanya by Ovk Co-Operative Housing Society Limited is a 33-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in October 2025 with possession due in December 2027. 0 units booked out of 3 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Chaitanya is a BMC-sanctioned project by Ovk Co-Operative Housing Society Limited in Borivali West, Mumbai 400092, registered with MahaRERA as PM1180002501072. It was launched in October 2025. It has 33 units in 1 building: 32 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 3 are for sale and 30 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
0 units booked out of 3 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 90%.