Empire Eternity, Borivali West
by Empire Land Developers LLP · Borivali West, Mumbai 400092 · Map
- Launched
- Dec 20252 yrs 7 mths promised
- Possession (MahaRERA)
- Jul 2028Not extended
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 7 of 1644% · 14 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 16 units
Rehab14 units for existing members
Total 30 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 7
- 2 BHK
- 8
- 3 BHK
- 9
- Other units
- 6
- Total units
- 30
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 16
- Rehab units
- 14
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 7 | |
| 100% | 30% | 0% | 5 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 7 mths | 2 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jul 2028 | Jul 2028 |
| Concrete structure (RCC) | 80% | 66% |
| Units booked (free sale) | 44% | 45% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- One Reserve, Borivali West
- The Crimson, Borivali West
- Manorama Jewel, Borivali West
- New Aakanksha Chsl, Borivali West
- Chaitanya, Borivali West
- Rishabraj Anuja, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| One Reserve | December 2025 | December 2030 | 0% | 14 units booked out of 23 units for sale |
| The Crimson | January 2026 | December 2030 | 0% | 0 units booked out of total 35 units |
| Manorama Jewel | January 2026 | August 2028 | 61% | 10 units booked out of total 35 units |
| New Aakanksha Chsl | October 2025 | February 2028 | 70% | 8 units booked out of 12 units for sale |
| Chaitanya | October 2025 | December 2027 | 90% | 0 units booked out of 3 units for sale |
| Rishabraj Anuja | October 2025 | June 2028 | 100% | 4 units booked out of 5 units for sale |
About this project
Empire Eternity by Empire Land Developers LLP is a 30-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in December 2025 with possession due in July 2028. 7 units booked out of 16 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Empire Eternity is a BMC-sanctioned project by Empire Land Developers LLP in Borivali West, Mumbai 400092, registered with MahaRERA as PM1180002501834. It was launched in December 2025. It has 30 units in 1 building: 24 homes (1, 2 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 16 are for sale and 14 are rehab units for existing members.
Its registered possession date is July 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.
7 units booked out of 16 units for sale (44%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 30% to 80%.