Rishabraj Anuja, Borivali West

by H Rishabraj Developers · Borivali West, Mumbai 400092 · Map

Launched
Oct 20252 yrs 8 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
4 of 580% · 29 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 5 units

Rehab29 units for existing members

Total 34 units. Rehab units are not for sale.

Project facts

1 BHK
2
2 BHK
32
Total units
34
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
5
Rehab units
29

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%4
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths3 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2028Nov 2028
Concrete structure (RCC)100%40%
Units booked (free sale)80%52%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rishabraj Anuja by H Rishabraj Developers is a 34-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in October 2025 with possession due in June 2028. 4 units booked out of 5 units for sale. The concrete structure (RCC) is complete.

Read full summary

Rishabraj Anuja is a BMC-sanctioned project by H Rishabraj Developers in Borivali West, Mumbai 400092, registered with MahaRERA as PR1180002501316. It was launched in October 2025. It has 34 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 5 are for sale and 29 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

4 units booked out of 5 units for sale (80%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.

Rishabraj's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA43
Total units across these projects1,514
Completed without extending the possession date22
Completed after an extension3
Lapsed3
Under construction15
Possession date extended on the builder's application4
Typical time from launch to 100% structure2 years 9 months
MahaRERA complaints (filed by or against the builder), all Rishabraj projects33 (4 of 43 projects)

See all Rishabraj projects →