Gurukrupa Ekam, Jogeshwari West

by Gurukrupa Realcon Infrabuild LLP · Jogeshwari West, Mumbai 400102 · Map

Launched
Nov 20253 yrs 5 mths promised
Possession (MahaRERA)
Apr 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
34 of 29112% · 127 rehab units
Buildings
21 acre
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale34 booked out of 291 units

Rehab127 units for existing members

Total 418 units. Rehab units are not for sale.

Project facts

2 BHK
114
3 BHK
221
Other units
83
Total units
418
Buildings
2
Land
1 acre
Phases
1
MahaRERA complaints
1
Free-sale units
291
Rehab units
127

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 50%Oct 2026: Excavation 50%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%34
50%0%0%34
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400102

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths4 yrs 11 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Apr 2029Dec 2030
Concrete structure (RCC)0%2%
Units booked (free sale)12%22%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Gurukrupa Ekam by Gurukrupa Realcon Infrabuild LLP is a 418-unit MHADA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in November 2025 with possession due in April 2029. 34 units booked out of 291 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Gurukrupa Ekam is a MHADA-sanctioned project by Gurukrupa Realcon Infrabuild LLP in Jogeshwari West, Mumbai 400102, registered with MahaRERA as PM1180002501525. It was launched in November 2025. It has 418 units in 2 buildings: 335 homes (2 and 3 BHK) and 83 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 418 units, 291 are for sale and 127 are rehab units for existing members.

Its registered possession date is April 2029, unchanged since launch. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.

34 units booked out of 291 units for sale (12%).

Gurukrupa Realcon's track record in Mumbai

MahaRERA projects registered 2019–2026 in Mumbai

Projects registered with MahaRERA25
Total units across these projects2,757
Completed without extending the possession date10
Completed after an extension2
Lapsed3
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure2 years 9 months
MahaRERA complaints (filed by or against the builder), all Gurukrupa Realcon projects3 (3 of 25 projects)