Sovrano, Jogeshwari West

by Lodha Developers Limited · Jogeshwari West, Mumbai 400102 · Map

Launched
Dec 2025First of 3 phases
Possession (MahaRERA)
Dec 2030 – Mar 2031Extended in 1 of 3 phases
Concrete structure
0%Weighted across 3 phases
Booked
58 of 36016% · 19 in Jul 2026
Buildings
33.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
14
2 BHK
222
3 BHK
116
4 BHK
8
Total units
360
Buildings
3
Land
3.3 acres
Phases
3
MahaRERA complaints
0

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Sovrano Tower-B
Early stage
PR11800025017431200%23%
Sovrano Tower C
Early stage
PR11800025017641200%25%
Sovrano Tower-A
Early stage
PR11800025017711200%0%
Show updates by phase

Sovrano Tower-B (PR1180002501743)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%28
80%0%0%13
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Sovrano Tower C (PR1180002501764)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%30
30%0%0%6
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Sovrano Tower-A (PR1180002501771)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
50%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 53%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

How to read construction stages

Compared with 5 similar projects in PIN 400102

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs4 yrs 5 mths
Possession date extendedYes0 of 5
Possession date (MahaRERA)Dec 2030 – Mar 2031Jun 2030
Concrete structure (RCC)0%3%
Units booked16%25%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Sovrano by Lodha Developers Limited is a 360-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, registered with MahaRERA in 3 phases, with possession dates from December 2030 to March 2031. 58 units booked out of total 360 units. Work on the concrete structure (RCC) has not started.

Read full summary

Sovrano is a BMC-sanctioned project by Lodha Developers Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as 3 phases (PR1180002501743, PR1180002501764, PR1180002501771). The first phase was launched in December 2025. Together the phases have 360 units in 3 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from December 2030 to March 2031; 1 of 3 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. None of the 3 phases has its structure complete.

58 units booked out of total 360 units (16%). Since the July 2026 update, 39 more units have been booked.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)