Autograph Residency, Jogeshwari West

by Multistar Builders LLP · Jogeshwari West, Mumbai 400102 · Map

Launched
Dec 20255 yrs promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
4%Mid-construction
Booked (free sale)
17 of 8919% · 209 rehab units
Buildings
21 acre
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale17 booked out of 89 units

Rehab209 units for existing members

Total 298 units. Rehab units are not for sale.

Project facts

1 BHK
197
3 BHK
66
Other units
35
Total units
298
Buildings
2
Land
1 acre
Phases
1
MahaRERA complaints
0
Free-sale units
89
Rehab units
209

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)4%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 57%Jul 2026: Excavation 83%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 4%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 4%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%4%0%17
83%0%0%14
57%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400102

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs4 yrs 8 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2030Sep 2030
Concrete structure (RCC)4%0%
Units booked (free sale)19%21%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Autograph Residency by Multistar Builders LLP is a 298-unit SRA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in December 2025 with possession due in December 2030. 17 units booked out of 89 units for sale. The concrete structure (RCC) is 4% complete.

Read full summary

Autograph Residency is an SRA-sanctioned project by Multistar Builders LLP in Jogeshwari West, Mumbai 400102, registered with MahaRERA as PR1180002501853. It was launched in December 2025. It has 298 units in 2 buildings: 263 homes (1 and 3 BHK) and 35 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 298 units, 89 are for sale and 209 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 4% complete, final finishes not started.

17 units booked out of 89 units for sale (19%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 4%.