Ghatkopar Tribhuvan Chsl, Ghatkopar East

by Rajeshree Enterprises · Ghatkopar East, Mumbai 400077 · Map

Launched
Nov 20252 yrs 4 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
60%Mid-construction
Booked (free sale)
1 of 1100% · 6 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 1 unit

Rehab6 units for existing members

Total 7 units. Rehab units are not for sale.

Project facts

2 BHK
5
3 BHK
2
Total units
7
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
1
Rehab units
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 35%Jul 2026: Excavation 35%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 60%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%1
35%0%0%–
35%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400077

Projects with up to 20 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths2 yrs 4 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Mar 2028Dec 2027
Concrete structure (RCC)60%80%
Units booked (free sale)100%29%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Ghatkopar Tribhuvan Chsl by Rajeshree Enterprises is a 7-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in November 2025 with possession due in March 2028. 1 unit booked out of 1 unit for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Ghatkopar Tribhuvan Chsl is a BMC-sanctioned project by Rajeshree Enterprises in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800081042. It was launched in November 2025. It has 7 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 7 units, 1 is for sale and 6 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

1 unit booked out of 1 unit for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 60%.