Ashtalakshmi Parradise Chsl, Malad West

by Samarpan Homes & Developers · Malad West, Mumbai 400064 · Map

Launched
Mar 20263 yrs 9 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 440% · 80 rehab units
Buildings
20.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 44 units

Rehab80 units for existing members

Total 124 units. Rehab units are not for sale.

Project facts

1 BHK
29
2 BHK
48
3 BHK
39
Other units
8
Total units
124
Buildings
2
Land
0.8 acres
Phases
1
MahaRERA complaints
0
Free-sale units
44
Rehab units
80

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation40%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 40%Oct 2026: Excavation 40%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 40%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
40%0%0%0
40%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths3 yrs 8 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Dec 2029Feb 2030
Concrete structure (RCC)0%0%
Units booked (free sale)0%1%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ashtalakshmi Parradise Chsl by Samarpan Homes & Developers is a 124-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in March 2026 with possession due in December 2029. 0 units booked out of 44 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Ashtalakshmi Parradise Chsl is a BMC-sanctioned project by Samarpan Homes & Developers in Malad West, Mumbai 400064, registered with MahaRERA as PM1180002503081. It was launched in March 2026. It has 124 units in 2 buildings: 116 homes (1, 2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 124 units, 44 are for sale and 80 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 40% complete, structure (RCC) not started, final finishes not started.

0 units booked out of 44 units for sale (0%).