Skip to main content

The Windsor - Mantri Smruti, Vile Parle East

by Ngs Windsor Realty LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Jan 20261 yr 11 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
6 of 1250% · 16 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 12 units

Rehab16 units for existing members

Land-owner share3 units, not for sale

Total 31 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
2
2 BHK
13
3 BHK
7
Other units
9
Total units
31
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
16
Land-owner share (not for sale)
3
Reserved units
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%6
100%0%0%6
0%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 11 mths2 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Mar 2028
Concrete structure (RCC)0%14%
Units booked (free sale)50%14%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

The Windsor - Mantri Smruti by Ngs Windsor Realty LLP is a 31-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in January 2026 with possession due in December 2027. 6 units booked out of 12 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

The Windsor - Mantri Smruti is a BMC-sanctioned project by Ngs Windsor Realty LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as PM1180002502008. It was launched in January 2026. It has 31 units in 1 building: 22 homes (1, 2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 12 are for sale, 16 are rehab units for existing members and 3 are the land-owner's share, not for sale.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

6 units booked out of 12 units for sale (50%).